Airport-Kamalapur Underground Metro Gains Momentum, Package-3 Utility Relocation to Begin This Month

Thursday, 15 October 2026 | 1:44 am | 100 times

Airport-Kamalapur Underground Metro Gains Momentum, Package-3 Utility Relocation to Begin This Month

Bangladesh’s first underground metro rail project is gaining fresh momentum, with utility relocation work at four underground stations under Package-3 of the Airport-Kamalapur route set to begin this month.

Md Sarwar Uddin Khan, project director of the Dhaka Mass Rapid Transit Development Project (MRT Line-1), disclosed the information on Wednesday.

He said the work would begin at Kamalapur, Rajarbagh, Malibagh and Rampura stations, all of which are included in Package-3. At the same time, utility relocation under Package-4 is progressing rapidly at Natun Bazar, Uttar Badda, Badda and Aftabnagar stations. Work at Uttar Badda, Badda and Aftabnagar began on January 20, 2025.

The project director said utility relocation has already been completed at Airport, Airport Terminal-3 and Khilkhet stations under Package-6, as well as at Narda station under Package-5.

According to project sources, construction of MRT Line-1 is being implemented through 12 packages. The main construction work began on February 2, 2023. The Bangladesh Army’s 24 Engineer Construction Brigade is responsible for relocating electricity, water, gas and other utility lines around the 12 underground stations into a common utility corridor. The work is being coordinated with the Dhaka Metropolitan Police’s traffic division to keep traffic moving normally in construction areas.

The 19.872-kilometre Airport Route will have 12 underground stations and connect Hazrat Shahjalal International Airport with Kamalapur Railway Station. Meanwhile, the 11.369-kilometre Purbachal Route will have seven elevated and two underground stations, connecting Natun Bazar with Purbachal.

Land development work for the project’s depot on 35.90 hectares of land at Pitalganj in Rupganj was completed on August 31. Although the initial target was to complete the work by March 2027, officials concerned said some components could continue until the end of next year.

The Japan International Cooperation Agency (JICA) is financing the project, while its revised budget was approved by the Executive Committee of the National Economic Council (ECNEC) on September 16.

Authorities expect MRT Line-1 to bring major changes to Dhaka’s transport system once operational, significantly reducing traffic congestion and pollution.