Shariatpur Correspondent
The 19 th span of Padma Multipurpose Bridge has been installed on 21-22 pillars, stretching the visible length up to almost 2.85 km.
Engineers of the bridge confirmed the news on Tuesday afternoon. A total of four span of Padma Bridge installed within less then one month . In this month another two spans will be set up during next week .
Assistance Engineer of Padma Bridge Human Kabir said “The 19 th span was installed around 2.00pm on Saturday”
The engineer also shared that two other spans will also be installed within this month.
“Meanwhile, the dream Padma Bridge will be completed after 41 spans installs on 42 pillars .
According to sources, the 6.15km-long bridge is being constructed of concrete and steel. The China Major Bridge Engineering Company from China has been constructing the main bridge, which is expected to be completed by June, 2021.