An example of prudent use of public funds has emerged in Dumuria upazila of Khulna, where Tk 13.63 million from the allocation for two canal re-excavation projects under the Employment Generation Programme for the Poorest (EGPP) has been returned to the government treasury.
The money remained unspent after the required work was completed under the supervision of the upazila administration and close monitoring by project implementation officials. The return of the unused funds has drawn appreciation from local residents, who believe that greater transparency and accountability in government projects could significantly reduce the misuse of public money.
According to the Upazila Project Implementation Office, a total of Tk 30,906,769 was allocated for re-excavating two canals in Raghunathpur and Sahas unions of Dumuria.
Under the projects, one canal was re-excavated from Krishnanagar Nimtala through Bil Dakatia to 80 feet south of Rangpur Saratala in Raghunathpur Union. The other project covered the stretch from Dolvanga Canal through Kathbunia Boro Doyan to the Bhodra River near Telikhali Gate in Sahas Union.
The projects aimed to create employment opportunities for extremely poor people while improving the area’s water drainage system. In addition to re-excavating the canals, around 5,000 fruit-bearing and medicinal saplings were planted in the project areas. Officials hope the initiative will also contribute to maintaining the local ecological balance.
Funds were spent on workers’ wages, equipment, transportation and other necessary expenses. After calculating the actual volume of work and associated costs, Tk 13,631,019 remained unspent from the total allocation. The amount was subsequently returned to the government treasury in accordance with financial rules.
Dumuria Upazila Project Implementation Officer (PIO) Md Arif Hossain said, “A total of Tk 30,906,769 was allocated for the re-excavation of the two canals. After meeting the necessary project expenses, Tk 13,631,019 remained. The entire amount has been deposited into the government treasury in accordance with the rules.”
However, not all of the planned work could be completed within the targeted scope. Officials said excessive rainfall and the natural characteristics of the soil prevented the authorities from completing the full excavation of the Krishnanagar Nimtala canal in Raghunathpur Union. Of the planned 7-kilometre stretch, 5.1 kilometres could be re-excavated.
Officials involved in the project said district- and upazila-level monitoring committees regularly reviewed the progress from the beginning to the completion of the projects. The volume of work completed, expenditure and overall progress were assessed periodically.
Dumuria Upazila Nirbahi Officer (UNO) Sabita Sarker said, “Every taka spent on a government project is public money. Therefore, ensuring its proper use is our responsibility. Bills were paid only for the amount of work actually completed in accordance with the rules. The remaining Tk 13,631,019 has been deposited into the government treasury as required.”
Local elected representatives and residents praised the decision to return the unused funds rather than spending the money unnecessarily. They said regular monitoring and accountability at every stage of project implementation could help prevent the wastage of public funds.
Meanwhile, the re-excavation of the two canals is expected to improve water drainage in the area. It could reduce waterlogging during the monsoon and improve irrigation facilities for agricultural land. Better drainage may also have a positive impact on agricultural production and the daily lives of local residents.
The Dumuria projects have emerged as a notable local example of financial transparency and accountability, demonstrating how paying bills according to the actual volume of work and returning unspent funds to the government treasury can help ensure the proper use of public money.