A major transformation may be on the horizon for Dhaka’s public transportation system. The government has taken an initiative to develop a new metro rail route from Gabtoli through Old Dhaka to Tarabo in Narayanganj.
Known as MRT Line-2, the proposed route is expected to cover approximately 35 kilometers and include 24 stations.
Parts of the route will be constructed as elevated tracks, while other sections will run underground. If implemented, the project would bring densely populated Old Dhaka directly into the metro rail network for the first time.
Cost to Exceed Tk 60,000 Crore
The estimated cost of the project has been set at Tk 60,837 crore. A significant portion of the funding is expected to come through foreign loans.
The government has sought approximately Tk 53,000 crore in loan assistance from the World Bank. Discussions are also underway with the Asian Infrastructure Investment Bank (AIIB) regarding project financing.
Areas the Metro Rail Will Pass Through
According to the current plan, the metro rail will begin at Gabtoli and pass through:
Dhaka Udyan → Basila Mor → Mohammadpur BRTC Bus Stand → Jigatola → Science Lab → New Market → Azimpur
From there, the route is planned to continue through:
Lalbagh → Chawkbazar → Mitford → Naya Bazar → Dholai Khal → Dayaganj → Kaptan Bazar → Demra → Tarabo in Narayanganj
There is also a proposal to construct a branch line from Gulistan to Sadarghat via Naya Bazar.
Old Dhaka’s Transport System Could Change Significantly
One of the most important aspects of the project is its plan to directly connect Old Dhaka to the metro rail network.
The densely populated area is home to a large population and is also one of the country’s major commercial centers.
Once the metro rail becomes operational, residents of Old Dhaka could benefit from faster transportation, while connectivity between major commercial areas and other parts of the capital could also improve.
Connections with Other Metro Rail Lines
MRT Line-2 is not being planned as an isolated project. Rather, it is intended to become an integral part of Dhaka’s broader metro rail network.
According to the plan:
Gabtoli: Connection with MRT Line-5
Kamalapur: Connections with MRT Lines 1, 4 and 6
Signboard: Connection with MRT Line-4
These connections would allow passengers to transfer more easily from one route to another, potentially creating a more integrated public transportation network across Dhaka.
Work Planned to Begin in Early 2027
Kabir Ahmed, head of the Physical Infrastructure Division of the Planning Commission, said that after receiving the Preliminary Development Project Proposal (PDPP) for MRT Line-2 from the ministry, it was reviewed and evaluated.
The proposal will now be sent to the Economic Relations Division (ERD) to secure foreign financing.
He described MRT Line-2 as a highly important transportation project because it would bring the densely populated and commercially significant Old Dhaka into the metro rail network.
The government plans to begin work on the project by the end of 2026 or early 2027. If the project proceeds according to plan, the target is to launch metro rail services on the route by 2030.
The project will be implemented by the Dhaka Mass Transit Company Limited (DMTCL). There are also plans to eventually extend the route from Narayanganj to Munshiganj.
How Much Could It Help Reduce Traffic Congestion?
A rapid public transportation connection between Old Dhaka, Gabtoli, Mohammadpur, Demra and Narayanganj could reduce pressure on Dhaka’s road-based transportation system.
It could also make travel between Dhaka and surrounding areas faster and more efficient.
However, securing the substantial financing required, managing the complexity of construction, and completing the project on schedule will be among the biggest challenges facing MRT Line-2.
If these obstacles can be overcome and the plan is successfully implemented, the new route could become an important link in Dhaka’s expanding metro rail network.