Rooppur Nuclear Power Plant Begins Second Phase of Trial Electricity Supply to National Grid

The Rooppur Nuclear Power Plant has begun its second round of trial electricity supply to the national grid. The connection process was initiated at 10:20 am on Monday (November 23).

Dr Md Kabir Hossain, Project Director of the Rooppur Nuclear Power Plant Construction Project, said approximately 300–350 megawatts of electricity would be supplied to the national grid during this phase for a period of 10 to 24 hours.

He said technical tests would be conducted during this period to assess the plant’s power generation system and its coordinated operation with the national grid.

Earlier, on November 17 at 3:16 pm, the Rooppur plant supplied approximately 350 megawatts of electricity to the national grid for the first time on a trial basis.

As part of the ongoing testing process, the plant has now commenced its second phase of trial electricity supply.