CHATTOGRAM, Dec 25, 2019 (BSS) – At least fifty percent construction work
of much-awaited dream Bangabandhu Tunnel under Karnaphuli river has so far
been completed, an official said.
Two tubes, stretching 2,450 meters each, are being constructed in the
tunnel as construction work of 1,220 meters of Anowara upazila-bound tube has
already been completed, its project director (PD) Engineer Harunur Rashid
Chowdhury told BSS on Tuesday.
He hoped the installations of rings in these tubes will be finished by next
May or June, if favorable weather prevails and no natural calamities take
place.
The two tubes comprise four lanes and each tube measures 35 feet wide and
16 feet high.
The total project works is expected to be completed by 2022.
The acquisition of 383 acres of land has also already been completed for
the tunnel’s approach roads.
Bangladesh Bridge Authority is constructing the 3.5 kilometers long
country’s first-ever four-lane Bangabandhu tunnel under Karnaphuli river with
an approach road of 4.89 kilometers alongside 740 meters of bridge linking
the main port city with southern regions of Chattogram, sources said.
Prime Minister Sheikh Hasina and the President of China Xi Jinping laid
foundation stone of the tunnel on October 14, 2017. Later Prime Minister
Sheikh Hasina inaugurated the boring work of the tunnel in February last.
The estimated cost of the tunnel is Tk. 9,880 crores, where Chinese Exim
Bank will provide 5,913 crores.
Chinese firm ‘China Communication Construction Company Ltd (CCCC), has
been appointed as consultant for construction of the tunnel.
The multilane tunnel route will pass through the river close to Navy
College on one side and Korean Export Processing Zone (KEPZ) and Karnaphuli
Fertiliser Company (KAFCO) on the other side.
The tunnel will connect Chattogram Port and Anowara Upazila and is
expected to make communication between Chittagong and Cox’s Bazar easier with
reducing traffic congestion on two bridges over the Karnaphuli river.